Last 25 builds Last 7 days Last 30 days Last 90 days All builds

Recent plan failures

Failed In Fixed In Time Taken To Fix
#24 Specs configuration updated

#26 Specs configuration updated

2 builds

18 minutes

#18 Specs configuration updated

#19 Specs configuration updated

1 build

3 minutes

#15 Specs configuration updated

#16 Specs configuration updated

1 build

6 minutes

#8 Specs configuration updated

#11 Specs configuration updated

3 builds

45 minutes

  • Average time to fix a failure: 18 minutes
  • Average number of builds between fixes: 1.75 builds
  • The longest time taken to fix a failure is 45 minutes, from failure starting in build #8.