a comprehensive HTML report from Allure test results.
None
Last 25 builds Last 7 days Last 30 days Last 90 days All builds

Recent plan failures

Failed In Fixed In Time Taken To Fix
#85 Changes by George Moellenbrock

#86 Changes by Kumar Golap

1 build

4 days, 2 hours, 18 minutes

#81 Changes by Kumar Golap

#83 Changes by Ville Suoranta

2 builds

1 day, 3 hours, 51 minutes

  • Average time to fix a failure: 2 days, 15 hours, 4 minutes
  • Average number of builds between fixes: 1.5 builds
  • The longest time taken to fix a failure is 4 days, 2 hours, 18 minutes, from failure starting in build #85.