Recent branch failures

Failed In Fixed In Time Taken To Fix
#1 First build for this plan

#4 Changes by Kumar Golap <kgolap@tizan.aoc.nrao.edu>

3 builds

6 weeks, 4 days, 22 hours, 40 minutes

  • Average time to fix a failure: 6 weeks, 4 days, 22 hours, 40 minutes
  • Average number of builds between fixes: 3 builds
  • The longest time taken to fix a failure is 6 weeks, 4 days, 22 hours, 40 minutes, from failure starting in build #1.
  • The greatest number of builds taken to fix a failure is 3, from failure starting in build #1.